A free SpecWindow project list. Records checked Oct 26, 2026; they can change after that date.
Missouri data center projects in government records, 2026
7 data center projects found in Missouri government records dated April 26 to October 26, 2026: Missouri DNR air permit applications and issued permits, Franklin County rezoning orders, and a City of Ferguson bond ordinance. 4 state equipment counts, including 483 generators proposed in an Amazon application near New Florence and 15 permitted gas turbines for a power plant the City of Independence says will supply the Nebius campus. Every project links to its government record.
Montgomery County and St. Louis city pages blocked automated reading, the Kansas City plan commission records could not be opened, and Public Service Commission dockets named no project, so projects in Kansas City, St. Louis city and much of rural Missouri may be missing. This is a sample, not a complete list.
Warrenton Data Center (22151 NW Service Road)
Warrenton, Warren County, Missouri
- Record
- Air construction permit 102026-007 (de minimis), Missouri DNR Air Pollution Control Program, issued Oct 8, 2026. dnr.mo.gov
- Applicant as named
- Warrenton DC Owner 1 LLC, Denver, Colorado (permit)
- Stage
- Permit issued. DNR issued construction permit 102026-007 for project 2026-05-031 on Oct 8, 2026, with a site limit of less than 40.0 tons of NOx a year. The permit says the data center will be mainly grid powered.
- Equipment stated
- Permitted: four Tier II CAT 3516E diesel emergency generator sets, each rated 3.0 MW, and two Clarke diesel fire pump engines rated 0.3 MW each, plus diesel belly and storage tanks.
Diamond Farms (Gateway Digital Campus), south side of I-44 between Highway 100, St. Mary's Road and Robertsville Road
Boles Township near Gray Summit, Franklin County, Missouri
- Record
- Rezoning orders 2026-256 and 2026-255 (W and R to A), County Commission meeting agenda, Sep 15, 2026. franklinmo.gov
- Applicant as named
- Diamond Farms, LLC (573.3 acres) and Diamond 66, LLC (39.5 acres) (orders). The orders do not state a use; the data center use and the Gateway Digital Campus name come from a press release published by The Missouri Times (Apr 23, 2026), which names Diamond Farms as the project
- Stage
- Zoning approved. The Planning and Zoning Commission recommended approval 8 to 1. The County Commission approved rezoning for the Gateway Digital Campus on Sep 15, 2026, reported by Spectrum News. The same agenda carries Order 2026-254, which permits data centers in the G and A districts.
- Equipment stated
- None stated in the records we opened.
Beltline Energy data center site (matched at medium confidence to BLE Landholdings), end of Phelan Road north of Highway O
Calvey Township south of Pacific, Franklin County, Missouri
- Record
- Rezoning order 2026-257 (W to A, about 490 acres), County Commission meeting agenda, Sep 15, 2026. franklinmo.gov
- Applicant as named
- BLE Landholdings, LLC (order). The order does not state a use. The data center use and the Beltline Energy name come from Spectrum News; we matched BLE Landholdings to Beltline Energy at medium confidence, by township, Highway O and the 4 to 5 Planning and Zoning vote, not by name
- Stage
- Zoning approved. The Planning and Zoning Commission vote failed 4 to 5, so the rezoning was not recommended. The County Commission approved rezoning for the Beltline Energy project on Sep 15, 2026, reported by Spectrum News.
- Equipment stated
- None stated in the records we opened.
Next Revolution Technologies redevelopment with data center, former Emerson campus (8000 West Florissant Avenue)
Ferguson, St. Louis County, Missouri
- Record
- Industrial revenue bond ordinance, Bill No. 7349 with administrative memorandum and plan, City of Ferguson, memo dated Sep 4, 2026. fergusoncity.com
- Applicant as named
- Next Revolution Technologies, LLC (bill)
- Stage
- Early land or zoning. The bill authorizes up to $22 billion in taxable industrial revenue bonds for a 217 acre redevelopment whose plan mentions a data center. The City Council approved the plan 4 to 3 on Sep 22, 2026, reported by St. Louis Public Radio (Sep 23, 2026), which also reported a potential future expansion for a 300 MW data center on the campus.
- Equipment stated
- None stated in the records we opened.
Independence Power Station 1 (21421 East Truman Road), power plant the City of Independence says will supply the Nebius data center campus
Independence, Jackson County, Missouri
- Record
- Air construction permit 072026-012 for a power plant, Missouri DNR Air Pollution Control Program, issued Jul 31, 2026. The permit does not mention a data center. dnr.mo.gov
- Applicant as named
- IPP Truman LLC, Dallas, Texas (permit). The permit does not mention a data center. The tie to the data center comes from a city government record: the City of Independence data center FAQ says the Nebius campus will need at least 800 MW, supplied by a new facility developed by Independence Power Partners at the City's retired Blue Valley Power Plant site. The FAQ does not name IPP Truman LLC or this permit; the match is by developer name and site.
- Stage
- Permit issued. DNR issued the permit on Jul 31, 2026 for a natural gas plant at the former Independence Power and Light Little Blue Valley coal plant site, as part of Phase 1 of the redevelopment of that property. The city FAQ says the plant will be built in phases and the initial phase will deliver 200 MW. The City Council approved a Chapter 100 tax abatement for the Nebius campus on Mar 2, 2026, before this window.
- Equipment stated
- Permitted for the power plant: fifteen Solar Titan 130 simple cycle natural gas combustion turbines rated 17.8 MW each (267.5 MW total) with SCR and oxidation catalysts, a 9.90 MMBtu/hr fuel gas heater, and one 500 kW diesel emergency generator. Data center equipment: none stated in the records we opened.
Project Spade Data Center (656 Tree Farm Road, south of I-70 near Highway 19)
New Florence, Montgomery County, Missouri
- Record
- Air construction permit application 2026-07-034 (de minimis), Missouri DNR pending permits list, administratively complete Jul 28, 2026. dnr.mo.gov
- Applicant as named
- Kinetic Site Ventures LLC (application). The application does not name Google; KBIA reports Project Spade as Google's data center (news only)
- Stage
- Permit pending. The application asks for a site NOx limit of 39.9 tons a year. The Montgomery County Commission approved a tax incentive package for the Google data center, reported by KBIA (Jun 11, 2026); we could not open the county record.
- Equipment stated
- Proposed in the application: eleven 3 MW Cummins QSK78-G37 diesel generators, four 500 kW Cummins QSX15-G9 generators and two 597 bhp diesel fire water pumps, with diesel or renewable diesel fuel.
Amazon Data Center, STL100 (near Hudson Road and Ellis Road)
New Florence, Montgomery County, Missouri
- Record
- Air construction permit application 2026-03-051, listed on the Missouri DNR pending permits list as administratively complete May 20, 2026. dnr.mo.gov
- Applicant as named
- Amazon Data Services, Inc. (application)
- Stage
- Permit pending. The application, dated Mar 14, 2026, asks for a minor construction permit with a site NOx limit of 99 tons a year and limits the emergency generators to 500 hours a year. Gov. Mike Kehoe announced a $10 billion Amazon data center in the county, reported by Spectrum News (Jun 15, 2026).
- Equipment stated
- Proposed in the application (not permitted): 483 diesel or renewable diesel emergency generators, including 476 CAT 3516E units rated 2.75 MW, four 1.6 MW units, one 400 kW unit and two 250 kW units, plus 17 storage tanks of 12,000 gallons.
Want a current report for Missouri or another state? A State Project Scan is a PDF report and Excel spreadsheet of the data center projects found in one state's government records from the last six months, with equipment reported as the underlying record states it: applicant as named, location, stage, next public dates, the buying window and a suggested next research step. Every row links to its government record.